This page will guide you through the process of getting started with the SQL Sync utility.

First, you need to decide if you want to do a sync or a diff. A sync is a way to maintain a Type-1 table, which shows what is currently in the source, plus what has been deleted. A diff is a way to maintain a Type-2 table, which shows what is currently in the source, and everything that has been there before.

If you're not sure about what you want, please read about Slowly Changing Dimensions.

In addition, the SQL Sync utility requires a few things to be true about your source data before you can start:

  1. Your source data should have a primary key of some kind. If you have duplicate rows you can't tell apart with no key, then you need to fix that problem first.
  2. The source table must have a datetime column that identifies when new rows are added to it.

...Ready to continue? Great!

Setting Up Your First Sync

There are 6 steps to set up your first sync.

  1. Implement custom code
  2. Pick names for things.
  3. Create the source and target tables
  4. Create a sync configuration
  5. Run it in debug mode
  6. Run it for real

Setting Up Your First Diff

There are 6 steps to set up your first diff.

  1. Implement custom code
  2. Pick names for things.
  3. Create the source and target tables
  4. Create a diff configuration
  5. Run it in debug mode
  6. Run it for real

Implement Custom Code

Begin and End Dates

There are two functions, dbo.GetBeginDate() and dbo.GetEndDate(), that return the datetime values for begin/end dates for a given table during a diff.

If you want to have custom logic for assigning begin/end dates to a table, you can edit the code in those functions to work however you want. That includes loading from a date/state table, if that will help.

Change GlobalInformationSchema

Before you can run any diff or sync processes, you need to update the dbo.GlobalInformationSchema view to include the database(s) you want to use for both source and target databases. There are examples in the view code.

Pick Names for Things

Create the source and target tables

The target table, surrogate key table, source table, and (optional) reconcile table must be created manually.

A surrogate key must be defined

The target table must have a primary key defined

Create a sync configuration

To set up a sync, follow this checklist:

Sync Config Checklist

  1. Enter the sync configuration into dbo.SyncConfig. See the description below, 'Configuring a Sync'
  2. Create the target table, if it doesn't already exist. Note: the target table must have a primary key defined
  3. If you want to have the sync create surrogate keys, create a surrogate key table (if it doesn't already exist)
  4. If you want to do a reconciliation, create the reconciliation table (if it doesn't already exist)

To configure a table synchronization, you must enter a row into the dbo.SyncConfig table. Each row in that table has all the metadata/configuration to synchronize 1 table (source-to-target).

There is a raw configuration template as well as an example configuration.

Create a diff configuration

Run in Debug Mode

Run it for real