Post-coding-deadline phase, runs during dissertation write-up. Target date leaves a ~1 week buffer before the Sep 7 submission deadline for final integration.
Due by August 31, 2026•0/1 issues closedAug 11-12
Due by August 12, 2026•0/2 issues closedAug 10 (1 day)
Due by August 10, 2026•0/1 issues closedAug 7-9
Due by August 9, 2026•0/5 issues closedAug 2-6. Highest overrun risk in the plan.
Due by August 6, 2026•0/3 issues closedJul 11-12 (compressed from 3 to 2 days by the one-day schedule shift), continues into Aug 2-6 after exam block
Overdue by 2 day(s)•Due by July 12, 2026•0/2 issues closedJul 10 (1 day) per plan-checklist.md
Overdue by 4 day(s)•Due by July 10, 2026•3/3 issues closed