Add PERT semantic anchor#355
Conversation
Co-authored-by: rdmueller <1856308+rdmueller@users.noreply.github.com> Agent-Logs-Url: https://github.com/LLM-Coding/Semantic-Anchors/sessions/918f688f-5676-406b-b848-a17d79474519
|
@rdmueller Looks good to me! 👍 |
|
@raifdmueller How is PERT related to the category "Statistical Methods" in the Semantic Anchors repository? |
Analysis of Proposed AnchorsEvaluated against the quality criteria: Precise, Rich, Consistent, Attributable. Summary
Detailed Analysis#354 P.A.R.A. Method —
|
|
Good question! PERT uses statistical concepts (three-point estimation, beta distribution, standard deviation σ = (P−O)/6) but its primary purpose is project scheduling, not statistical analysis. The PR correctly places it under The connection to A |
PERT (Program Evaluation and Review Technique) is a well-established stochastic project scheduling method developed in 1958 for the US Navy's Polaris programme. It was missing from the anchor catalog despite being widely used for effort estimation under uncertainty.
Added files
docs/anchors/pert.adoc— English anchor covering three-point estimation, the PERT formula (E = (O + 4M + P) / 6), standard deviation (σ = (P − O) / 6), network diagrams, critical path, and probabilistic schedulingdocs/anchors/pert.de.adoc— German translationUpdated catalog/data
website/public/data/anchors.json— PERT entry understrategic-planning; roles: product-owner, business-analyst, team-lead, consultant, educator; related: moscow, user-story-mapping, impact-mappingskill/semantic-anchor-translator/references/catalog.md— PERT entry added to Strategic Planning section so agents can discover and suggest itOriginal prompt