Day 0: Init new development cycle
To be done until: 2026-06-14 (Sunday)
3rd week: Beta phase
To be done until: 2026-07-02 (Thursday)
To be done at: 2026-07-04 (Saturday)
To be done at: 2026-07-05 (Sunday)
To be done from: 2026-07-05 - 2026-07-11 (Sunday before release - Thursday before release)
2 days before the release
To be done until: 2026-07-09 (Thursday)
Release
To be done at: 2026-07-11 (Saturday)
Release announcements
To be done at: 2026-07-12 (Sunday)
Day 0: Init new development cycle
To be done until:
2026-06-14(Sunday)CHANGELOG.txt(in thedevbranch)aSOFTWARE_NAME10_5dietpi-globals(in thedevbranch) withG_DIETPI_VERSION_CORE,G_DIETPI_VERSION_SUB,G_DIETPI_VERSION_RCidentical to the values in fileversion(see above)dietpi-survey_reportversion on server3rd week: Beta phase
To be done until:
2026-07-02(Thursday)masterand remove indev.To be done at:
2026-07-04(Saturday).0RC versionTo be done at:
2026-07-05(Sunday)To be done from:
2026-07-05-2026-07-11(Sunday before release - Thursday before release).1and.2RC versions2 days before the release
To be done until:
2026-07-09(Thursday)Release
To be done at:
2026-07-11(Saturday)Release announcements
To be done at:
2026-07-12(Sunday)