@@ -18,7 +18,7 @@ Guideline
1818
.. gd_guidl:: Release Management Guideline
1919
:id: gd_guidl__rel_management
2020
:status: valid
21-
:complies: std_req__iso26262__management_64131, std_req__iso26262__management_64132, std_req__iso26262__management_64133
21+
:complies: std_req__iso26262__management_64131, std_req__iso26262__management_64132, std_req__iso26262__management_64133, std_req__iso26262__management_64135
2222

2323
.. _workflow_release:
2424

process/process_areas/release_management/guidance/release_templates.rst

Lines changed: 13 additions & 13 deletions
Original file line numberDiff line numberDiff line change
@@ -93,16 +93,16 @@ Templates
9393
:status: valid
9494
:complies: std_req__iso26262__management_64131, std_req__iso26262__management_64132, std_req__iso26262__management_64133
9595

96-
Copy the below steps into the release ticket:
97-
98-
Release <add version number> for <platform/module_name>
99-
-------------------------------------------------------
100-
101-
1. Link this issue to the correct milestone and assign to the technical lead
102-
2. Check respective Verification report on the release candidate's github tag
103-
3. Check bugfixes or justify failed tests
104-
4. Check the safety package completeness (includes "valid" documents and work products status, supported by the safety manager)
105-
5. Create/update the release note (pull request to close this issue)
106-
6. Document safety manager's "recommendation to release" by asking his GitHub review approval of the release note
107-
7. Create the "release" in GitHub according to :need:`gd_guidl__rel_management`
108-
8. Merge PR and close this issue to complete the release
96+
| Copy the below steps into the release ticket:
97+
|
98+
| Release <add version number> for <platform/module_name>
99+
| -------------------------------------------------------
100+
|
101+
| 1. Link this issue to the correct milestone and assign to the technical lead
102+
| 2. Check respective Verification report on the release candidate's github tag
103+
| 3. Check bugfixes or justify failed tests
104+
| 4. Check the safety package completeness (includes "valid" documents and work products status, supported by the safety manager)
105+
| 5. Create/update the release note (pull request to close this issue)
106+
| 6. Document safety manager's "recommendation to release" by asking his GitHub review approval of the release note
107+
| 7. Create the "release" in GitHub according to :need:`gd_guidl__rel_management`
108+
| 8. Merge PR and close this issue to complete the release