ADR 0010 — Plan-Driven DAG Execution

Status

Accepted — amended by iron-comms unification (2026-07-01): task-list push transport changed, see Amendment below and ADR-0020

Context

The agent previously executed modules in a hardcoded foreach (var module in jobModules) loop. The loop happened to produce the correct order only because DI registration order matched the intended execution order — an accidental invariant. The loop had four structural problems:

  1. No dependency enforcement. IModule.DependsOn was documented but not acted upon. A configuration change or future module addition could silently run WorkItems import before Identities import, producing corrupt target state.
  2. No parallelism. Export modules read from the source system independently — there is no data dependency between them. The sequential loop introduced unnecessary latency.
  3. No task-level resume. Cursor-based checkpointing (ADR-0003) handles item-level resume within a module. If the agent crashed mid-job, the new agent had no record of which modules had already completed and re-executed them all.
  4. No visibility before execution. Operators connecting to a running job had no structural view of what the agent was about to do.

Decision

The Agent builds an execution plan from IModule.DependsOn declarations, persists it, and drives all execution from the plan.

Plan build:

  1. At job start, IJobExecutionPlanBuilder.BuildPlanAsync reads the enabled modules and their DependsOn graphs.
  2. Modules with no remaining dependencies form an execution tier and run concurrently.
  3. When all tasks in a tier complete, the next tier is evaluated. Tiers are processed sequentially; tasks within a tier are processed concurrently.
  4. If a task fails, tasks in subsequent tiers that depend on the failed task are marked Skipped with a skipReason referencing the failed dependency. Tasks in the same tier with no dependency on the failed task continue.
  5. A circular dependency graph causes an InvalidOperationException before any module executes.

Plan persistence:

  • The plan is persisted to .migration/Checkpoints/plan.json via IStateStore immediately after build, before the first module executes.
  • The plan is pushed to the Control Plane so clients can display the full task list before any work begins. (Originally via IControlPlaneTelemetryClient.PushTaskListAsync; see Amendment.)
  • On resume, if plan.json exists in the package, the plan is reloaded rather than rebuilt. Tasks with status: Running (crashed mid-way) are reset to Pending. Tasks with status: Completed are not re-executed. ForceFresh deletes plan.json and rebuilds.

Relationship to ADR-0003: Cursor-based checkpointing operates at the item level within a single module. Plan-level checkpointing operates at the task level across modules. Both coexist: the plan skips completed-module re-execution; the cursor skips already-processed items within a resumed module.

Alternatives Considered

Static ordering by DI registration convention: What the platform had before. Brittle — any change to DI setup order silently changes execution order.

Fully sequential, dependency-ignorant execution: Safe but slow. Does not satisfy parallelism or dependency enforcement requirements.

External workflow engine (Temporal, Durable Functions): Provides DAG execution, persistence, and parallelism but adds an infrastructure dependency. The package-based plan achieves the same outcomes without external services.

Consequences

  • IModule.DependsOn is now authoritative — the plan executor enforces it, not registration order.
  • Independent modules (e.g., Identities, Nodes, Teams on export) run concurrently by default.
  • WorkItems import cannot start until both Identities and Nodes import complete.
  • Operators see the full task list with statuses in the TUI/CLI before any module executes (fed by GET /jobs/{id}/bootstrap).
  • A crash followed by a restart re-uses the persisted plan — previously completed tasks are skipped, not re-run.
  • Circular dependency declarations are a job-start failure, not a runtime failure partway through.

Amendment — Iron-Comms Unification (2026-07-01)

IControlPlaneTelemetryClient / PushTaskListAsync and the POST /agents/lease/{leaseId}/tasks endpoint have been removed. Task-list push now flows through UnifiedWorkerEventWriter.EnqueueTasks as a Tasks-kind event in the batched POST /workers/{workerId}/events channel (both the net10 JobAgentWorker and net481 TfsJobAgentWorker). The decision itself — plan-driven DAG execution with the plan pushed before any work begins — is unchanged.