heat to power conversion efficiency result comparison with reference, refine injection temperature comment
1 parent 2e1694a commit bbf629f

6 files changed

Lines changed: 12 additions & 8 deletions

File tree

docs/Fervo_Project_Cape-5.md.jinja

Lines changed: 1 addition & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -321,6 +321,7 @@ See [GEOPHIRES Economic Outputs documentation](parameters.html#economic-paramete
321321
| Maximum Net Electricity Generation | {{ max_net_generation_mwe}} MW | | |
322322
| Maximum Total Electricity Generation | {{ max_total_generation_mwe }} MW | Upper bound: 600 MW | Combined nameplate capacity of 10×60 MWe Gen 2 ORCs. A total of 8×60 MWe Gen 2 ORCs have been announced for Phase II; 3 from Turboden and 5 from Baker Hughes (Turboden, 2025; Jacobs, 2025). This equates to 480 MW gross capacity for Phase II's 400 MW net capacity. An equivalent SOAK 500 MW project would therefore require 10 Gen 2 ORC units. (Note that the modular Gen 2 ORCs are not individually modeled in this case study, and are assumed to be combined into a single power plant.) |
323323
| 2-year Average Net Power Production per Production Well | {{ two_year_avg_net_power_mwe_per_production_well }} MW | 7.6–11.5 MW | Figures 4 and 12 (Singh et al., 2025). |
324+
| Heat to Power Conversion Efficiency | {{ heat_to_power_conversion_efficiency_pct ~ '%' }} | 19.5% | DeGolyer and MacNaughton, 2024. |
324325
| Injection Pumping Parasitic Load <br/> ({Average Pumping Power}/{Average Total Electricity Generation}) | {{ parasitic_loss_pct ~ '%' }} | Upper bound: 16.7% | The Phase II procurement strategy (480 MW gross / 400 MW net) implies a design ceiling of 16.7% for total on-site consumption (including injection pumping). Current SOAK targets for parasitic consumption range from 15–20%, reflecting a planned reduction from the ~25–30% observed in Phase I operations (Norbeck, 2026). |
325326
| Total fracture surface area per well | {{ total_fracture_surface_area_per_well_mm2 }}×10⁶ m² <br/> ({{ total_fracture_surface_area_per_well_mft2 }} million ft²) | Project Red: 2.787×10⁶ m² <br/> (30 million ft²) | Greater fracture surface area expected than Project Red (Fercho et al., 2025). |
326327
| Reservoir Volume | {{ reservoir_volume_m3 }} m³ | | Calculated from fracture area × fracture separation × number of fractures per well × number of wells |

src/geophires_docs/generate_fervo_project_cape_5_md.py

Lines changed: 3 additions & 0 deletions
Original file line numberDiff line numberDiff line change
@@ -387,6 +387,9 @@ def n_year_avg_net_power_mwe(years: int) -> float:
387387
'max_net_generation_mwe': round(sig_figs(max_net_generation_mwe, 3)),
388388
'max_total_generation_mwe': round(sig_figs(max_total_generation_mwe, 3)),
389389
'two_year_avg_net_power_mwe_per_production_well': sig_figs(two_year_avg_net_power_mwe_per_production_well, 2),
390+
'heat_to_power_conversion_efficiency_pct': sig_figs(
391+
_q(surf_equip_sim['Heat to Power Conversion Efficiency']).to('percent').magnitude, 3
392+
),
390393
'parasitic_loss_pct': sig_figs(parasitic_loss_pct, 3),
391394
'number_of_times_redrilling': redrills,
392395
'total_wells_including_redrilling': total_wells_including_redrilling,

tests/examples/Fervo_Project_Cape-5.out

Lines changed: 2 additions & 2 deletions
Original file line numberDiff line numberDiff line change
@@ -6,8 +6,8 @@ Simulation Metadata
66
----------------------
77
GEOPHIRES Version: 3.13.8
88
Simulation Date: 2026-05-20
9-
Simulation Time: 11:24
10-
Calculation Time: 1.875 sec
9+
Simulation Time: 11:38
10+
Calculation Time: 1.855 sec
1111

1212
***SUMMARY OF RESULTS***
1313

tests/examples/Fervo_Project_Cape-5.txt

Lines changed: 2 additions & 2 deletions
Original file line numberDiff line numberDiff line change
@@ -102,7 +102,7 @@ Number of Multilateral Sections, 0, -- This parameter is set to 0 because, for t
102102
Production Flow Rate per Well, 107, -- Cape Station pilot testing reported a sustained flow rate of 95–100 kg/s and maximum flow rate of 107 kg/s (Fervo Energy, 2024). Modeling by Singh et al. suggests initial flow rates of 120–130 kg/sec that gradually decrease over time (Singh et al., 2025). The case study flow rate is chosen both as a conservative target for long-term sustainability and to achieve a more economically favorable drawdown and redrilling schedule.
103103
# The ATB Advanced Scenario models sustained flow rates of 110 kg/s (NREL, 2024).
104104

105-
Production Well Diameter, 8.535, -- Inner diameter of 9⅝ inch casing size, the next standard casing size up from 7 inches, implied by announcement of increasing casing diameter (Fervo Energy, 2025).
105+
Production Well Diameter, 8.535, -- Inner diameter of 9⅝ inch casing size, the next standard casing size up from 7 inches, implied by announcement of "increasing casing diameter" (Fervo Energy, 2025).
106106
Injection Well Diameter, 8.535, -- See Production Well Diameter
107107

108108
Production Wellhead Pressure, 303 psi, -- Modeled at a constant 300 psi in Singh et al., 2025. We use a marginally uprated value to conform to GEOPHIRES's calculated minimum wellhead pressure and nominally align with the gradual increase in WHP for constant flow rates modeled by Singh et al.
@@ -111,7 +111,7 @@ Injectivity Index, 1.38, -- Based on ATB Conservative Scenario (NREL, 2025) dera
111111
Productivity Index, 1.13, -- See Injectivity Index
112112

113113
Ramey Production Wellbore Model, True, -- Ramey's model estimates the geofluid temperature drop in production wells
114-
Injection Temperature, 53.6, -- Calibrated with GEOPHIRES model-calculated reinjection temperature (Beckers and McCabe, 2019). Close to upper bound of Project Red injection temperatures (75–125℉; 23.89–51.67℃) (Norbeck and Latimer, 2023). Note: GEOPHIRES enforces a thermodynamic optimum that overrides higher values, such as Fervo's considered operational target of 80°C (DeGolyer and MacNaughton, 2024; intended for silica scaling mitigation), resulting in a "maximum theoretical power" scenario. Support for higher reinjection temperatures may be added in future GEOPHIRES versions.
114+
Injection Temperature, 53.6, -- Calibrated with GEOPHIRES model-calculated reinjection temperature (Beckers and McCabe, 2019). Close to upper bound of Project Red injection temperatures (75–125℉; 23.89–51.67℃) (Norbeck and Latimer, 2023). Note: GEOPHIRES enforces a thermodynamic optimum that overrides higher values, such as the 85°C ORC outlet temperature specified in Cape Station's plant design (DeGolyer and MacNaughton, 2024) (intended for silica scaling mitigation), resulting in a "maximum theoretical power" scenario. Support for higher reinjection temperatures may be added in future GEOPHIRES versions.
115115
Injection Wellbore Temperature Gain, 3, -- Empirical estimate for high-flow rate wells where rapid fluid velocity minimizes heat uptake during descent (Ramey, 1962).
116116

117117
Maximum Drawdown, 0.0025, -- This value represents the fractional drop in production temperature compared to the initial temperature that is allowed before the wellfield is redrilled. It is calibrated to maintain the PPA minimum net electricity generation requirement. It is a very small percentage because it is relative to the initial production temperature; the temperature quickly rises higher due to thermal conditioning and plateaus until breakthrough, so any drawdown relative to the initial value signals that the temperature has already declined from its stabilized peak.

tests/examples/Fervo_Project_Cape-6.out

Lines changed: 2 additions & 2 deletions
Original file line numberDiff line numberDiff line change
@@ -6,8 +6,8 @@ Simulation Metadata
66
----------------------
77
GEOPHIRES Version: 3.13.8
88
Simulation Date: 2026-05-20
9-
Simulation Time: 11:24
10-
Calculation Time: 1.876 sec
9+
Simulation Time: 11:38
10+
Calculation Time: 1.842 sec
1111

1212
***SUMMARY OF RESULTS***
1313

tests/examples/Fervo_Project_Cape-6.txt

Lines changed: 2 additions & 2 deletions
Original file line numberDiff line numberDiff line change
@@ -98,7 +98,7 @@ Number of Multilateral Sections, 0, -- This parameter is set to 0 because, for t
9898
Production Flow Rate per Well, 100
9999
# The ATB Advanced Scenario models sustained flow rates of 110 kg/s (NREL, 2024).
100100

101-
Production Well Diameter, 8.535, -- Inner diameter of 9⅝ inch casing size, the next standard casing size up from 7 inches, implied by announcement of increasing casing diameter (Fervo Energy, 2025).
101+
Production Well Diameter, 8.535, -- Inner diameter of 9⅝ inch casing size, the next standard casing size up from 7 inches, implied by announcement of "increasing casing diameter" (Fervo Energy, 2025).
102102
Injection Well Diameter, 8.535, -- See Production Well Diameter
103103

104104
Production Wellhead Pressure, 303 psi, -- Modeled at a constant 300 psi in Singh et al., 2025. We use a marginally uprated value to conform to GEOPHIRES's calculated minimum wellhead pressure and nominally align with the gradual increase in WHP for constant flow rates modeled by Singh et al.
@@ -107,7 +107,7 @@ Injectivity Index, 1.38, -- Based on ATB Conservative Scenario (NREL, 2025) dera
107107
Productivity Index, 1.13, -- See Injectivity Index
108108

109109
Ramey Production Wellbore Model, True, -- Ramey's model estimates the geofluid temperature drop in production wells
110-
Injection Temperature, 53.6, -- Calibrated with GEOPHIRES model-calculated reinjection temperature (Beckers and McCabe, 2019). Close to upper bound of Project Red injection temperatures (75–125℉; 23.89–51.67℃) (Norbeck and Latimer, 2023). Note: GEOPHIRES enforces a thermodynamic optimum that overrides higher values, such as Fervo's considered operational target of 80°C (intended for silica scaling mitigation), resulting in a "maximum theoretical power" scenario. Support for higher reinjection temperatures may be added in future GEOPHIRES versions.
110+
Injection Temperature, 53.6, -- Calibrated with GEOPHIRES model-calculated reinjection temperature (Beckers and McCabe, 2019). Close to upper bound of Project Red injection temperatures (75–125℉; 23.89–51.67℃) (Norbeck and Latimer, 2023). Note: GEOPHIRES enforces a thermodynamic optimum that overrides higher values, such as the 85°C ORC outlet temperature specified in Cape Station's plant design (DeGolyer and MacNaughton, 2024) (intended for silica scaling mitigation), resulting in a "maximum theoretical power" scenario. Support for higher reinjection temperatures may be added in future GEOPHIRES versions.
111111
Injection Wellbore Temperature Gain, 3, -- Empirical estimate for high-flow rate wells where rapid fluid velocity minimizes heat uptake during descent (Ramey, 1962).
112112

113113
Maximum Drawdown, 0.0025, -- This value represents the fractional drop in production temperature compared to the initial temperature that is allowed before the wellfield is redrilled. It is calibrated to maintain the PPA minimum net electricity generation requirement. It is a very small percentage because it is relative to the initial production temperature; the temperature quickly rises higher due to thermal conditioning and plateaus until breakthrough, so any drawdown relative to the initial value signals that the temperature has already declined from its stabilized peak.