Critical Path

The critical path in a project is indicated by a single task or a series of tasks in a project, critical path describes the calculated start date or end date of a project. If a task in a critical path is delayed, then the entire project will be delayed.

The critical path can be enabled in Gantt by using built-in toolbar button or showCriticalPath method.

Using Toolbar Icon

You can enable/disable the critical path in Gantt by using toolbar button, and this button can be enabled in the Gantt toolbar by using the following code example.

{% highlight javascript %}

<ej-gantt id="GanttControl" [toolbarSettings]="toolbarSettings">

{% endhighlight %}

{% highlight javascript %}

import {Component} from '@angular/core';

@Component({ selector: 'ej-app', templateUrl: 'app/app.component.html', }) export class AppComponent { public toolbarSettings: any; constructor() { this.toolbarSettings = { showToolbar: true, toolbarItems: [ //.. "criticalPath", ], }, } }

{% endhighlight %}

Click here to view the online demo sample for critical path in Gantt.

Using Method

You can enable the critical path by using showCriticalPath**()** method with parameter as true. And critical path can be disabled using the same method with parameter as false.

{% highlight html %}

<button id="buttonon" (click)="show($event, item)">Critical Path On <button id="buttonoff" (click)="hide($event, item)">Critical Path Off //...

{% endhighlight %}

{% highlight javascript %}

import {Component} from '@angular/core';

@Component({ selector: 'ej-app', templateUrl: 'app/app.component.html', }) export class AppComponent { public toolbarSettings: any; constructor() { //... } public show(event, item) { var obj = $("#GanttControl").ejGantt("instance"); obj.showCriticalPath(true); } public hide(event, item) { var obj = $("#GanttControl").ejGantt("instance"); obj.showCriticalPath(false); } }

{% endhighlight %}

Customizing critical path background

You can customize the critical task background by setting custom color codes to the critical task elements’ class names,

Taskbar–.e-ganttchart .e-criticaltaskbar

Progressbar–.e-ganttchart .e-criticalprogressbar

Connector line–.e-ganttchart .e-criticalconnectorline

Connector line left arrow– .e-ganttchart .e-criticalconnectorlineleftarrow

Connector line right arrow– .e-ganttchart .e-criticalconnectorlinerightarrow

write the following code in app.component.css file

{% highlight html %}

.e-ganttchart .e-criticaltaskbar {
            background-color : #ffb366!important;
            border-color : gray!important
}
.e-ganttchart .e-criticalprogressbar {
            background-color : #ff99cc!important;
            border-color : #b35900!important
}
.e-ganttchart .e-criticalconnectorline {
            background-color : #b800e6!important;
}
.e-ganttchart .e-criticalconnectorlineleftarrow {
            border-right-color : #b800e6!important;
}
.e-ganttchart .e-criticalconnectorlinerightarrow{
            border-left-color : #b800e6!important;
}

{% endhighlight %}

{% highlight javascript %}

import {Component} from '@angular/core';

@Component({ selector: 'ej-app', templateUrl: 'app/app.component.html', styleUrls: ['app/app.component.css'] }) export class AppComponent { public toolbarSettings: any; constructor() { //... } }

{% endhighlight %}