Overview
This issue tracks the implementation of support for the Model Context Protocol revision 2025-06-18. This includes all transient changes from the original 2024-11-05 specification through the intermediate 2025-03-26 revision to the final 2025-06-18 specification.
📋 Complete Revision History
2024-11-05 → 2025-03-26 → 2025-06-18
Original: 2024-11-05 (HTTP+SSE transport, basic features)
Intermediate: 2025-03-26 (StreamableHTTP, OAuth 2.1, JSON-RPC batching)
Target: 2025-06-18 (Structured output, elicitation, resource links, removed batching)
🎯 Implementation Plan
The upgrade is organized into 6 phases covering all transient changes:
Phase 1: Core Protocol Updates (Critical) ⚠️ Breaking Changes
Phase 2: Transport Layer Modernization (Critical) ⚠️ Breaking Changes
Phase 3: Enhanced Tool System (High Priority)
Phase 4: Interactive Features (High Priority)
Phase 5: Security & Enterprise Features (Medium Priority)
Phase 6: Quality of Life Improvements (Low Priority)
⚠️ Major Breaking Changes Required
From 2024-11-05 → 2025-03-26
- Transport Architecture: HTTP+SSE → StreamableHTTP
- Authorization: Basic auth → OAuth 2.1 framework
- Batching: Single requests → JSON-RPC batching support
- Content Types: Text/Image → + Audio support
From 2025-03-26 → 2025-06-18
- JSON-RPC Batching: REMOVED (was added in 2025-03-26)
- Tool Output: Text responses → Structured output format
- Protocol Headers: Optional → REQUIRED MCP-Protocol-Version
- Lifecycle: SHOULD → MUST for lifecycle operations
🚀 Timeline
- Phase 1: ✅ COMPLETED (Protocol updates)
- Phase 2: Week 2-3 (Transport modernization)
- Phase 3: Week 4-5 (Enhanced tools)
- Phase 4: Week 6 (Interactive features)
- Phase 5: Week 7 (Security & enterprise)
- Phase 6: Week 8 (Quality of life)
🔄 Migration Strategy
Backward Compatibility Windows
- 2024-11-05 Transport: Maintain during Phase 2 implementation
- JSON-RPC Batching: Implement in Phase 2, remove in Phase 3
- Legacy Tool Output: Support during Phase 3 transition
- Feature Flags: Enable gradual migration
Deprecation Timeline
- HTTP+SSE Transport: Deprecated in Phase 2, removed in Phase 6
- JSON-RPC Batching: Added Phase 2, removed Phase 3 (per 2025-06-18)
- Simple Tool Responses: Deprecated Phase 3, removed Phase 6
📊 Success Criteria
🔗 Related Issues & PRs
Phase 1 (Completed)
Phase 2 (Transport Modernization)
Phase 3 (Enhanced Tools)
Phase 4 (Interactive Features)
Phase 5 (Security & Enterprise)
Phase 6 (Quality of Life)
⚠️ Risk Assessment
High Risk
- Transport layer replacement may break existing integrations
- OAuth 2.1 implementation has security implications
Medium Risk
- Structured tool output requires significant refactoring
- Elicitation framework adds complexity to tool execution
Low Risk
- Enhanced logging and metadata features are additive
- Audio content support is optional enhancement
📚 Documentation Updates Required
Revision-Specific Guides
Technical Documentation
Overview
This issue tracks the implementation of support for the Model Context Protocol revision 2025-06-18. This includes all transient changes from the original 2024-11-05 specification through the intermediate 2025-03-26 revision to the final 2025-06-18 specification.
📋 Complete Revision History
2024-11-05 → 2025-03-26 → 2025-06-18
Original: 2024-11-05 (HTTP+SSE transport, basic features)
Intermediate: 2025-03-26 (StreamableHTTP, OAuth 2.1, JSON-RPC batching)
Target: 2025-06-18 (Structured output, elicitation, resource links, removed batching)
🎯 Implementation Plan
The upgrade is organized into 6 phases covering all transient changes:
Phase 1: Core Protocol Updates (Critical)⚠️ Breaking Changes
Phase 2: Transport Layer Modernization (Critical)⚠️ Breaking Changes
Phase 3: Enhanced Tool System (High Priority)
Phase 4: Interactive Features (High Priority)
Phase 5: Security & Enterprise Features (Medium Priority)
Phase 6: Quality of Life Improvements (Low Priority)
From 2024-11-05 → 2025-03-26
From 2025-03-26 → 2025-06-18
🚀 Timeline
🔄 Migration Strategy
Backward Compatibility Windows
Deprecation Timeline
📊 Success Criteria
🔗 Related Issues & PRs
Phase 1 (Completed)
Phase 2 (Transport Modernization)
Phase 3 (Enhanced Tools)
Phase 4 (Interactive Features)
Phase 5 (Security & Enterprise)
Phase 6 (Quality of Life)
High Risk
Medium Risk
Low Risk
📚 Documentation Updates Required
Revision-Specific Guides
Technical Documentation